County Settlement Paves the Way for Moody Lane Extension; Sets Course for Salary Study

Churchill County has reached a settlement with a developer that clears the way for its Moody Lane–Coleman Road Connector Project (MLCRC). The project includes construction of a new bridge over the Carson River and an extension of Moody Lane south to Coleman Road, terminating east of the Onde Verde subdivision. The plan requires rights-of-way through several properties, including more than 155 acres owned by River Homes In Fallon, LLC (RHF).

The property is located east of the golf course and spans from the Carson River north to Rice Road. River Homes In Fallon, LLC is owned by the River Homes In Fallon Management Trust from Las Vegas. The settlement document lists Steve Mack and Sherri Hughes as signators; both are listed online as leaders of Bravo Store Systems, a 40-year-old company that creates business management software for retailers like pawn shops and gun stores. 

In the settlement agreement, RHF maintains it has several potential legal claims against the county “for inverse condemnation of real property, including water rights, pre-condemnation damages, and breach of a Water Banking and Dedication Agreement dated April 18, 2012 (“RHF Claims”) and the County contests the RHF Claims.”

RHF began its Fallon project in 2005 with a planned unit development (PUD) for two parcels totaling 155.25 acres. The company was unable to continue development due to financing issues, and the county extended the PUD for 15 years. Assistant County Manager Joe Sanford said the county declined to renew the PUD in 2020 because the development was based on outdated land-use maps.

Under the new agreement, the county will receive a right-of-way through RHF’s property in exchange for a release of potential legal claims. RHF plans to rezone its property for residential and commercial uses. The deal resolves potential claims, secures the right-of-way for the MLCRC project, and provides zoning needed for future development.

The county’s cost totals $125,188.30, including $114,855 in abated wastewater operations and maintenance (O&M) fees over five years and $10,333.30 in waived outstanding wastewater O&M fees and finance charges.

The settlement grants RHF R-3 zoning, allowing up to 661 residential units, including a maximum of 330 apartment units, and 15 acres of commercial development. Although the PUD has expired, the new zoning will guide future land use. Commissioners approved the agreement unanimously.

In other business, commissioners authorized the Human Resources Department to begin a salary compensation study to ensure county wages remain competitive. Previous studies were completed in 2015, 2018, and 2022. Sanford presented two options: conducting the study internally or hiring an outside vendor. Quotes from vendors ranged from $52,750 to $92,000. Commissioners early on indicated a preference for using an external firm to avoid any appearance of bias.

District Attorney Art Mallory and Chief Deputy District Attorney Lane Mills urged the commission to include a private-sector comparison in the study, noting that both the District Attorney’s and Public Defender’s offices have struggled to retain and recruit attorneys due to pay disparities.

Commissioners voted to use an outside vendor and directed Sanford to organize a workshop for vendors to present their proposals.

Commissioners also approved $450 per day in holiday standby pay for district attorneys, public defenders, and the Justice of the Peace. State law requires arrestees to receive a bail hearing within 48 hours, including weekends and holidays. The new rate takes effect Oct. 15, 2025, with one-time retroactive payments for work performed on July 4 and Sept. 1, 2025. Funding will come from the Department of Indigent Defense Services and will cover nine holidays in fiscal year 2025–2026.

 

More about the author/authors:
Share
Rate

Comment

Comments

August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 1
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 2
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 3
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 4
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 5
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 6
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 7
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 8
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 9
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 10
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 11
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 12
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 13
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 14
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 15
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 16
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 1 Page no. 1
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 2 Page no. 2
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 3 Page no. 3
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 4 Page no. 4
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 5 Page no. 5
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 6 Page no. 6
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 7 Page no. 7
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 8 Page no. 8
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 9 Page no. 9
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 10 Page no. 10
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 11 Page no. 11
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 12 Page no. 12
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 13 Page no. 13
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 14 Page no. 14
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 15 Page no. 15
August 21, 2026 -CCSD Bus Drivers Are Ready to Rol - page 16 Page no. 16
COMMENTS
Comment author: Johnathan Skinner Comment text: I have known Jorge for decades. Anyone who even heard about will tell you he was aging and createdan incredible legacy. Comment publication date: 8/17/26, 7:40 PM Comment source: Jorge Jose Guerrero Comment author: Patti Cole Comment text: Marie will be forever treasured in memories. The memories remain of a soft-spoken, seemingly unassuming but determined individual who absolutely knew what path she wanted to take in life, and followed it. Her instinctive reactions, which highlighted her steadfast level of love and caring for her family, friends and all living things found in nature, hold lessons for us all. An unexpected splash of her self-deprecating humor, coupled with uncanny timing, will always bring a smile. For me, Marie lives on in the sighting of a Black-crowned night heron in the tules, the bloom of a beautiful spring flower and, most poetically, in the struggle of wildlife photographers handling their very large camera lenses. Comment publication date: 8/15/26, 9:31 AM Comment source: Obituary-Marie Dong Ko Comment author: John Chaney Comment text: I just figured out that Betty was my 1st cousin. Her dad Ted was my dad's brother. I never knew Ted or Betty, but I wish I did. I am 73 and live in IL. I am building my family tree and see where Betty has fit in. Blessings to you Curt and family. Comment publication date: 8/14/26, 11:04 AM Comment source: Obituary - Betty Lou (Chaney) Anderson Comment author: Karen Webb Comment text: I am so sorry to hear this. I loved coming to the carwash to see John! He always made my day. Prayers for all of his family during this difficult time. Comment publication date: 8/11/26, 8:56 PM Comment source: In Memory of John Evans
SUPPORT OUR WORK